Mid & West Wales Fire & Rescue Service
Resin Flooring Law, Order and Blue Light

Mid & West Wales Fire & Rescue Service

Appliance bay flooring refurbishment across four operational fire stations

Project Ref MWWFRS

Client
Mid & West Wales Fire & Rescue Service
Location
Mid and West Wales
Project Size
410m²
Start Date
February 2026
Duration
8 weeks (phased)
Sector
Law, Order and Blue Light
Products
Resdev Pumadur HF

Project Overview

TPS360 refurbished appliance bay floors across four operational fire stations, installing a 6mm Resdev Pumadur HF, FeRFA Type 8 heavy-duty polyurethane resin screed suited to appliance traffic and regular washing.

The work went beyond the surface finish, with floor removal, pit infilling and replacement screeds where required. Levels were adjusted around thresholds and drainage before resin installation. Safe firefighter access was maintained while the stations continued responding to emergency calls.

On Film

Project Video

Fire Station Appliance Bay Resin Flooring

Scope of Works

The Specification

  1. 01

    Strip-Out

    Removal of existing tiles and screeds

  2. 02

    Preparation

    Mechanical substrate preparation

  3. 03

    Pit Infill

    Infilling redundant inspection pits

  4. 04

    Screeds

    Replacement screeds and drainage falls

  5. 05

    Levels

    Adjustment of floor levels at thresholds

  6. 06

    Resin Screed

    6mm Resdev Pumadur HF, FeRFA Type 8

  7. 07

    Detailing

    Resin coving and step details

  8. 08

    Joints

    Reinstatement of floor joints

On Site

The Challenges

The stations remained operational, with appliances parked outside and safe firefighter access maintained. Dust, plant and material movements were managed around emergency calls.

Floor removal exposed differing substrate conditions, requiring changes to screed depths and levels around thresholds and drainage. Accurate levelling and sufficient curing were essential before heavy appliances could return.

  • Four stations kept operational throughout
  • Safe firefighter access maintained
  • Works planned around emergency calls
  • Differing substrate conditions under old floors
  • Curing time before heavy appliances returned

The important work started beneath the resin. We had to get the base sound and the levels right at thresholds and drains before we could think about the finish. Those details matter when you're putting heavy appliances back into the bays and washing the floors regularly.

Scott Barclay Director, TPS360
Gavin Ashcroft

Meet Our Specialist

Gavin Ashcroft

Sales Director (South Wales & West)

Gavin Ashcroft, our Sales Director for South Wales and West, leads the resin flooring team, bringing vast experience in both resin flooring and hygienic solutions. Gavin has made a huge contribution through his food and beverage industry knowledge and expertise, working with leading food production plants throughout the UK.

Let's Talk About Your Next Project

Tell us about your site and your programme and we'll come back to you with the right approach.